![]() |
|
08.13.03Lambeau Field renovation to be finished on time and within budget
High profile project completed without any major problems
A recent interview with John Jones, Packers' chief operating officer
With an agreement in place that any cost overruns on the massive $295 million of Lambeau Field in Green Bay would go to the Green Bay Packers or its construction management team, there was tremendous pressure to keep the high-profile project from going into the red.
Weve had to a lot of things go right on this project. We learned to be flexible and
look for opportunities to accelerate the project in certain areas. And weve been practical. We know we cant do everything. Weve had to make choices.
John Jones, Green Bay Packers And as construction crews put the finishing touches on the renovation project in the weeks before the Packers first exhibition game on August 23, those efforts have paid off. The project is going to finish on time and within its budget, a rare occurrence for a huge construction project, said Stuart Zadra, project manager for Hammes Co., a Brookfield construction management which is overseeing the project for the Green Bay Packers. Weve had to a lot of things go right on this project, said John Jones, executive vice president and chief operating officer for the Packers. We learned to be flexible and look for opportunities to accelerate the project in certain areas. And weve been practical. We know we cant do everything. Weve had to make choices. Zadra said the renovation was difficult and complicated, but construction crews were able to overcome the obstacles and complete it on time. We have flexible in terms of the way we completed the project because it was not like building an office building or a hotel, said Zadra, as he walked through the new atrium on the northern end of the stadium recently. We were renovating a stadium that was still very active. We had people, other than construction crews, in here everyday. And some days, we had more than 60,000 people on our construction site. Hectic work site
In all, 4,200 construction workers went through the projects safety training program. Zadra said an average of 400 workers were on the site daily, with the peak employment at about 1,200 during the winter and spring of 2002, the most hectic part of the project. Currently, there are about 200 workers on the project as it is about 95 percent complete. On an average day, about $900,000 worth of construction work was completed, with about $20 million being spent a month at the peak of the project.According to the Packers and the Stadium District overseeing the project, about $87 million, of the first $248 million spent on the project, was paid to Brown County businesses, and $181.9 million to Wisconsin-based business. The project, one of the largest ever in the state, is being funded with a mix of private and public money. A 0.5 percent in Brown County is being used to pay for the interest and principal on $160 million of the project cost. The rest of the funding came from a one-time user fee on Packer season-ticket holders, proceeds from a Packers stock sale and a loan from the National Football League. It involved increasing the stadiums capacity from 60,890 to 71,000, including 6,260 new club seats and 167 luxury boxes. A second concourse was added to the new stadium as well as additional restrooms and concession areas. Titletown, a new five-story atrium, will house the Packer Hall of Fame, the Packer Pro Shop and a restaurant. The renovation, which was started in 2000, was divided into three phases, with the first calling for the construction of the two suites towers on the east and west sides of the stadium, and the erection of the structural frame of the 365,000-square-foot atrium. The second phase relocated team offices and locker rooms to the new area and completed the reconfiguration of the seating bowl, including the installation of new mechanical systems to run the stadium. And the third phase was the completion of the stadium bowl, installation of two new scoreboards and other work in the north and south end zones. Tough choices
Zadra said the key to getting the project done on time and within budget were the flexibility of the construction crews and the Packers. He said construction managers were continuously looking for ways to speed up the schedule, sometimes at a higher price.There is no doubt the economy helped this project especially as we went along. There were also a lot of construction workers looking for work and wanting to work on this job. Timing is everything and on this project, things have just worked out for the best.
Stuart Zadra, Hammes Co. We knew we had to make tough choice and we were ready to do that, Jones said. If we had a list of five things construction crews would like to do, most time we do the top two or three, that ones that will have the most positive impact on the project. Zadra and Jones said the project benefited from a number of factors, including a sluggish economy which lowered material prices, three mild winters that allowed crews to accomplish more work than planned and a strong workforce that took a lot of pride in the project. Jones said throughout the renovated building, construction crews had etched their initials in many nooks and crannies to show their involvement in the project. They are in places where no one will ever see them, but the crews will know they are there and that they were part of this project, he said. And while the economic downturn hurt many businesses, Jones said it had helped lower the cost of materials. He said the project had received as many as eight bids on steel, compared to two. And nine different people contacted the team asking about the work to build the statues of Vince Lombardi and Curly Lambeau that will stand outside the atrium On the steel purchases, the bids were not only lower than expected, they were all within the same range, something that is unusual in construction bidding, Zadra said. There is no doubt the economy helped this project especially as we went along, Zadra said. There were also a lot of construction workers looking for work and wanting to work on this job. Timing is everything and on this project, things have just worked out for the best. Zadra said construction crews also worked very closely with the Packers and architects to limit the amount of change orders on the project. While there were some change orders, they were no where the level or for the amount of money that would be expected on a project of this size, he said. I think the biggest claim we have out there right now is in the thousands of dollars range, he said. Normally on a project like this, you would have some claims in the millions of dollars. Weve really worked hard to make sure that we understood the project and its challenges. |
Kass' Archives
10.23.03
Heard on the streetThompson to get December jury trial Clarke comes out firing on police station boondoggle Fan favorites Cubs rank higher than Bucks or Brewers 10.08.03
Heard on the streetWill Walker finally get a challenger? Folaron takes shots at Milwaukee Police Chief Jones Feingold takes on Rove Henningsen still hanging around City Hall 09.29.03
Judges ruling saved former Alderman Henningsen eight additional months in prison
09.24.03
Police Chief Jones files paper to raise funds for Milwaukee mayoral race
09.22.03
Henningsen likely to serve more than eight months in federal prisonWho will replace Bo? Thompson no stranger to court system JCC using school yard analogies to raise funds in Whitefish Bay expansion fight 09.11.03
HHS Secretary Thompsons brother charged with sexual assault
09.07.03
The real reason Colon dropped out of mayors raceDid Doyle take his own Harley parade jaunt? New career for Henningsen? Summerfest Board could make decision on Blacks future this week 08.27.03
Walker seeks tax freeze pledge from Milwaukee County communitiesWhat will Pratt do as acting mayor? DOT contends Sen. George's Marquette request is unlawful 08.18.03
Some Pawlinski contributors dont want money back
08.13.03
Heard on the streetCan Clarke win? And when will he finally announce he is running for mayor? Barrett to hold own kickoff event George rips Doyle on minority involvement plans for Marquette Interchange 08.13.03
Lambeau Field renovation to be finished on time and within budget
07.31.03
Heard on the streetBlacks Summerfest successor list already being compiled Chicago mayoral race connection Darrow said to considering run for U.S. Senate City trying to lure grocery store downtown 07.22.03
Heard on the streetBlack already looking at job options Speculation increases that Clarke ready to announce mayoral bid Norquist, George continue their sparring match Downtown Milwaukee could be getting new ice cream parlor 07.07.03
Heard on the streetBlack seeking buyout Barrett raises more than $200,000 Wisconsin Center Board to get code of conduct Major New Berlin development finally moving ahead after snake problem 07.07.03 a.m.
Looking for more bucks
06.24.03
Heard on the streetSeveral aldermen looking to try and derail Pratt's elevation to acting mayor Barrett told to shed 'Mr. Nice Guy' image DNR recommends expansion of ozone non-attainment zone Neighborhood group calls on Henningsen to resign 06.19.03
Sykes speaks
06.17.03
Heard on the streetPratt apparently weighing mayoral options Norquist committed to finishing out term Price tag to be mayor could top $1.25 million 06.09.03 p.m.
Heard on the streetGimbel not likely to be reappointed to Wisconsin Center Board MPS union spouse expected to get $141,250 in salary and benefits to help improve city schools MPS forced to return more than $1 million in technology grants Doyle kills proposal to expand nonattainment zone in political decision 06.09.03 a.m.
Levy to bring its difference to Milwaukee
06.03.03 a.m.
Heard on the streetBarret ready to jump into Mayors race Rockettes coming to Milwaukee Brewers going door to door Harley Announces parade 06.03.03 a.m.
MPS deputy superintendent leaving for Washington, D.C.
05.29.03
Boston firms last ditch effort to snatch Wisconsin Center catering contract fails
05.22.03 p.m.
Blacks future with Summerfest not to be decided until after festival
05.22.03 p.m.
Judge quickly throws out Boston Firms attempt to derail Midwest Airlines catering contract
05.16.03 p.m.
Opposition grows to Door County against proposed new coal-fired plants in Oak Creek
05.16.03
Boston firm pushes for another chance at lucrative convention center catering contract
05.13.03 p.m.
With Pawlinski agreeing to plea, federal probe not expected to produce any more charges
05.12.03
Alderman Pawlinski likely to resign as part of plea agreement
05.09.03
Wisconsin Center Board selects Levy for controversial catering contract
05.07.03 p.m.
Summerfest Board meeting to decide Blacks future cancelled at last minute
05.07.03 a.m.
Blacks future likely to be decided by Summerfest Board Thursday
05.07.03
Food Games
|